      request #5133 Start/End date displayed under the Sprint title on the Agile Dashboard includes week-ends
    Infos
    #5133
    Patricia Carrasco (pcar)
    2013-11-13 09:00
    2013-09-23 21:27
    5303
    Details
    Start/End date displayed under the Sprint title on the Agile Dashboard includes week-ends
    The Start/End date displayed under the Sprint title on the Agile Dashboard includes week-ends where the Burndown Graph does not.
    Agile Dashboard
    6.3
    Empty
    • [ ] enhancement
    • [ ] internal improvement
    Empty
    Stage
    Empty
    Closed
    2013-11-13
    Attachments
    References

    Follow-ups

    User avatar
    Mass Change

    • Status changed from Verified (disabled) to Verified
    • Is an Enhancement or an internal improvement? set to