    Computed calculation is broken for old projects
    Given a tracker A with a computed field which as a computed field total effort and who has a target field name effort estimate and which is checked as Fast compute.
    Given an other tracker B with a computed field named total effort for a target field effort_estimate,
    the calcul must display the correct value.
    Trackers
    8.16
    Empty
    • [ ] enhancement
    • [ ] internal improvement
    Empty
    Stage
    Marie Ange Garnier (marieange)
    Closed
    2016-07-21
    Attachments
    Empty
    References

    Follow-ups

    User avatar

    Merged in Tuleap 8.16.99.83


    • Status changed from Under review to Closed