      request #10681 Burndown report does not work when start date is after the last remaining effort
    Infos
    #10681
    Marie Ange Garnier (marieange)
    2017-09-27 10:16
    2017-09-22 10:43
    10910
    Details
    Burndown report does not work when start date is after the last remaining effort
    How to reproduce issue:
    - you should work on an old burndown (issue is sql is due to TO_DAYS(FROM_UNIXTIME(0))),
    so I you try to tricks date, you won't be able to reproduce
    - last changeset date of artifact should be < to start date
    (given my last remaining effort for my artifact is 17-11-2016, then I will
    reproduce issue when my start date is > to 18-11-2016)
    - start_date should be inferior to today
    Trackers
    Empty
    Empty
    • [ ] enhancement
    • [ ] internal improvement
    Empty
    Stage
    Empty
    Closed
    2017-09-27
    Attachments
    Empty
    References

    Follow-ups

    User avatar
    Thomas Gerbet (tgerbet)2017-09-27 10:16
    Integrated into Tuleap 9.12.99.45.

    • Category set to Trackers
    • Status changed from Under review to Closed
    • Connected artifacts
    • Close date set to 2017-09-27
    User avatar
    • Summary
      -Burndown report does not work when start date is after the first remaining effort 
      +Burndown report does not work when start date is after the last remaining effort 
    User avatar
    • Summary
      -Burndown report does not work when start date is before the first remaining effort 
      +Burndown report does not work when start date is after the first remaining effort 
    • Original Submission
      Something went wrong, the follow up content couldn't be loaded
      Only formatting have been changed, you should switch to markup to see the changes