Given the following data

  • On Sept 2, #123 is created with status "New"
  • On Sept 4, #99 is updated with status "Closed"
  • On Sept 10, #124 is created with status "New"
  • On Sept 11, #124 is updated with status "On going"
  • On Sept 12, #124 is updated with status "Closed"
  • On Sept 23, #78 gets a comment + a remaining effort change
  • On Oct 10, #77 is updated with status "Declined"
  • On Oct 11, #222 is created with status "New"
  • On Oct 12, #223 is created with status "New"
  • On Oct 12, #223 is updated with status "Closed"

The chart renderer over September and October (per month) will be a cummulative bar chart:

For Sept:

  • New: #123
  • Closed: #99, #124

For Oct:

  • Closed: #223
  • Declined: #77

Comments (questions ?):

  • On Sept, #78 got updated but is not displayed because there is no status change
  • On Oct, #123 is no longer shown as "New" because there were no change

The underlying calculation:

  • For a given period (month), take into account all artifacts with a status change (in previous example, #78 is excluded from counts)
  • Take the last status as the end of time period (the intermediate states are not displayed, as for #124 and #223, calculation is done on Sept 30 and Oct 31 respectively)
Empty
Status
Empty
Ready (stalled)
Development
  • [ ] Does it involves User Interface? 
  • [ ] Are there any mockups?
  • [ ] Are permissions checked?
  • [ ] Does it need Javascript development?
  • [ ] Does it need a forge upgrade bucket?
  • [ ] Does it need to execute things in system events?
  • [ ] Does it impact project creation (templates)?
  • [ ] Is it exploratory?
Empty
Details
#12540
Manuel Vacelet (vaceletm)
2019-09-09 17:52
2018-11-21 10:58
4209

References
Referencing story #12540

Artifact Tracker v5

epic #2047 Tracker

Follow-ups

User avatar
A few feelings & suggestions :
- if I had to track "status updates populations", I would use some positive/negative bar chart, i.e. # of INs [during the specified time period] above X-axis, # of OUTs below (ideally with trend dotted lines between successive bars) ;
- here is described more of a "derivative CFD", tracking "status populations update" instead. It may simply be a helper to CFD retrospective analysis.

This matter could be envisioned as a larger Lean/Kanban KPIs Epic (given that Scrum is more featured in Tuleap so far), as would also be of interest :
- artifact status history (cumulative status durations for every artifact of the report)
- status duration distribution (# of artifacts having been in a given status selection for as long as X) => lead & cycle times etc.
- completion estimates for ready or ongoing artifacts with respect to their current column & relative position in the Kanban, to some (maybe hand-saved) array of status mean durations, and optional artfacts' estimated "points" ;
... or merely, in the first place, a pre-digested (somewhat structured) API output specifically designed for status history reporting.

  • Category set to
User avatar
  • Acceptance criteria
    Something went wrong, the follow up content couldn't be loaded
    Only formatting have been changed, you should switch to markup to see the changes
User avatar
  • Acceptance criteria
    Something went wrong, the follow up content couldn't be loaded
    Only formatting have been changed, you should switch to markup to see the changes
User avatar
  • Acceptance criteria
    Something went wrong, the follow up content couldn't be loaded
    Only formatting have been changed, you should switch to markup to see the changes