•  
      request #11108 Time scale on burnup chart displayed in weeks
    Infos
    #11108
    Patricia Carrasco (pcar)
    2018-02-07 14:23
    2018-02-06 14:44
    11431
    Details
    Time scale on burnup chart displayed in weeks
    The duration of the sprint is 10 days which is pretty standard. Despite of this, the time scale is displaying in weeks. If you change the duration of the sprint to 5 days, it then displays in days.
    Agile Dashboard
    9.17
    Empty
    • [ ] enhancement
    • [ ] internal improvement
    Emilio Palmiero (empa), Stephan Bill (stephanbill)
    Stage
    Empty
    New
    Empty
    Attachments
    References
    References list is empty

    Follow-ups

    User avatar
    Hi, it should be consistent with burndown. For my sprint tracker, I'm displaying the burnup and burndown. Thanks
    User avatar
    Thomas Gorka (tgorka)2018-02-07 14:14
    Hi,

    Your sprint lasts 10 working days but the global duration including week-ends worth approximately 15 days (enough to switch the display in weeks).

    However, I agree to say the script should not take weekends into account to deduce the right time frame to use and that it has to be fixed.
    User avatar
    Thomas Gorka (tgorka)2018-02-07 08:51
    Hello,

    The granularity of the time scale is set up accordingly to the duration of the sprint. As of today, the thresholds are respectively:

    • From 2 days to 2 weeks -> Dates are displayed as usual.
    • From 2 weeks to 3 months -> Weeks are displayed
    • More than 3 months -> Months are displayed.

    We can increase the limit for dates, but we have to stay reasonable or the X axis will become barely readable because label will overlap themselves.

    I propose the following solution:

    From 2 days to 3 weeks -> Dates are displayed as usual.

    This way, dates are displayed for sprints lasting up to 15 days, but it is the very limit.

    Please find in attachment two screen-shots illustrating my explanations.

    What do you think about that?