•  
      request #11341 Updating status of a service specific to a project updates the status of all services specific to this project
    Infos
    #11341
    Thomas Gerbet (tgerbet)
    2018-04-05 13:52
    2018-04-03 18:37
    11669
    Details
    Updating status of a service specific to a project updates the status of all services specific to this project
    System services are not impacted.
    Project admin
    All
    Empty
    • [ ] enhancement
    • [ ] internal improvement
    Empty
    Stage
    Empty
    Closed
    2018-04-05
    Attachments
    Empty
    References

    Follow-ups

    User avatar

    Integrated in Tuleap 9.19.99.27


    • Status changed from Under review to Closed
    • Connected artifacts
    • Close date set to 2018-04-05
    User avatar
    Thomas Gerbet (tgerbet)2018-04-03 18:45
    A patch is under review: gerrit #10954.

    • Summary
      -Update status of a service specific to a project updates the status of all service specific to this project 
      +Updating status of a service specific to a project updates the status of all services specific to this project 
    • Status changed from Under implementation to Under review