      request #8343 Automatically set field value from parent
    Infos
    #8343
    Jonathan (jod)
    2015-08-17 17:09
    2015-08-17 12:39
    8468
    Details
    Automatically set field value from parent
    Hi,

    We are using the Agile Dashboard trackers, including Stories and Tasks. We've added a field 'Team' on the stories are several teams are working on the same project and thus the same backlog.

    This field is also added to the Tasks, and we wanted to assign its value directly from the Story 'team', when a new child Task is created under a Story.

    Is it currently possible ? I haven't find a way to do it. If not, I think that it may be a good improvement.

    Regards
    Agile Dashboard
    8.5
    CentOS 6
    • [x] enhancement
    • [ ] internal improvement
    Empty
    Stage
    Empty
    Waiting for information
    Empty
    Attachments
    Empty
    References
    References list is empty

    Follow-ups

    User avatar
    You are right, I miss read the description.

    There is no such a feature in Tuleap as of today
    User avatar
    Jonathan (jod)2015-08-17 14:23
    I have tried it but it doesn't really answer to my needs.

    In fact, in our workflow, the story are created first, and assigned to a team during the Sprint planning. This means that the 'team' field is set previously to any task creation, and must not be modified after.

    Then, when the team starts to work on a story, they create the children tasks. It's during this phase that the task team field should be populated automatically. They could set the team manually but this is a bit tricky.
    User avatar
    In Tracker administration of your Story tracker you should be able to define a Trigger (Workflow section).

    This trigger would be:
    Set field "Team" with value "A" when "at least one children "Task" field "team" is set to "A"

    Does it fit your needs ?

    • Status changed from New to Waiting for information