      request #8655 Display Capacity and Effort value in sprint planning view
    Infos
    #8655
    Patrick Renaud (patrick.renaud)
    2018-01-10 09:30
    2015-12-02 23:16
    8778
    Details
    Display Capacity and Effort value in sprint planning view
    In the sprint planning view, it would be very useful to display the current release's capacity and effort values near the start-end dates on the screen.

    To get these values I have to navigate up to the Top Planning view and open the Release milestone in question. It would be much *much* appreciated if such values would be displayed in the sprint planning screen, where I happen to spend the most of my time in practice.
    Agile Dashboard
    Empty
    Empty
    • [x] enhancement
    • [ ] internal improvement
    patricia.carrasco@ericsson.com
    Stage
    Empty
    Closed
    2018-01-10
    Attachments
    References
    References list is empty

    Follow-ups

    User avatar
    But Manuel, I don't quite understand the technical challenge here. The wanted data is already displayed in the milestone planning view - all I am proposing is to display that same data in the release backlog view as well.

    Or am I missing an obvious point...?
    User avatar
    That's a good idea however it's complex from a technical stand point, esp. if we expect this part to be dynamically updated.

    As of today the angular scope of planning is inside the tab "Planning" so to achieve that, we would need to enlarge the scope of Angular to the whole page (not a bad thing as it's the long term goal).